|
William
R. Snodgrass Tennessee Tower Building Emergency Replacement of Electrical
Buss Duct System Customer
Profile: In
September 2003, the William R. Snodgrass Tennessee Tower State Building was hit
by lightning. This caused a power outage and put the building under emergency
power. The sprinkler system malfunctioned, thinking there was a fire, it began
to release water. This continued until the building flooded. Because of severe
water damage to the electrical system, the State called Stones River Electric,
the holder of their electrical maintenance contract.
Customer
Issues: The
State stressed that they needed their building functional within 48 hours. This
required immediate response in multiple areas. We needed to assess the damage,
understand the load requirements on each floor, create a temporary resolution,
prepare a plan of action to provide power to the building, notify the local utility
and codes department of our actions, coordinate delivery of material, and complete
the temporary repair in just 48 hours. Project
Objective: After
analyzing the situation, we discovered that the Electrical Buss Duct System (EBDS)
was severely damaged. It would have to be replaced. The delivery time for new
Buss Duct would be two weeks. We devised a plan with the State and Local Codes
to temporarily restore power to the building until the new EBDS could be installed.
Results:
Utilizing
46 men and three managers, we worked around the clock for 48 hours in order to
temporarily repair this major electrical emergency. To create acceptable working
conditions, we demolished 1400 ft. of 1600-amp EBDS and installed several 500
mcm cables to temporarily feed the electrical system on each floor, while we waited
for the EBDS to be manufactured. Then, we connected all electrical rooms from
floors 5-27 to the cables. Two weeks later, when the new EBDS was delivered, we
worked two crews simultaneously around the building’s hours of operation. One
crew laid out the buss duct before the building opened in the morning, and a second
crew installed the EBDS at night to keep from disrupting employees. The entire
project was complete within a two week time frame. Stones River Electric, was
able to complete the project within the expected time frame of the State Officials
as well as put smiles on their faces.
|